Project news

The Privé Construction Progress – November 2026: Phase 1 Topping Out and Structural Milestones

By DnD Realty
Tiến độ dự án The Privé công trường Phase 1 tháng 10/2026

Content reviewed by Ms Khả Hân, co-founder of DnD Realty with more than 10 years in high-end property.

Key Takeaways
Updated 11/11/2026 · Source: developer progress notices and DND Realty site photos
  • Lead Tower Milestone: Block 8 cast its 32nd floor slab, its topmost residential floor. BLUEMARQ held the Phase 1 Topping Out Ceremony on November 7, 2026.
  • Phase 1 Cluster: Block 7 reached floor 27; Block 5 and Block 6 reached floor 26 under general contractor Hoa Binh Construction Group (HBC).
  • Phase 2 Cluster: Block 12 reached floor 19; Block 9 reached floor 17; Block 10 reached floor 15; Block 11 reached floor 12 under contractor CSCEC.
  • Development Scale: 42,903.8 m² (~4.3 hectares), 12 towers rising 32 to 33 storeys, total 3,175 units (2,093 units approved under Sales Permit 3126/SXD-PTDT).
  • Expected Handover: Phase 1 (Towers 5, 6, 7, 8) expected in Q3/2027; Phase 2 (Towers 9, 10, 11, 12) expected in Q1/2028.
  • Sales Gallery: 12A Vu Tong Phan, An Phu Ward (Roundabout A12, Vu Tong Phan Street, Binh Trung Ward), Thu Duc City, open 08:30–18:00 daily.
Updated: November 11, 2026 · Source: BLUEMARQ Development progress releases, on-site topping out documentation, and DND Realty field surveys

The Privé is a riverside residential enclave developed by Dat Xanh Group in partnership with BLUEMARQ Development, situated on the Nam Rach Chiec peninsula along Song Hanh Road in Thu Duc City. Embraced on three sides by the Giong Ong To River, the 4.3-hectare community features twelve high-rise residential towers rising 32 to 33 storeys. Eight towers are currently under vertical construction across two development phases. The project reached an important milestone on November 7, 2026 with the Phase 1 topping out ceremony. DND Realty provides this reverse-chronological field analysis covering on-site developments from November 2026 and October 2026. This review details structural height comparisons across all eight towers, certified project milestones, and advisory guidance for international property investors.

The Prive construction progress panoramic view of eight towers along the river in late October 2026
Photo: Construction site, late October 2026. Panoramic flycam perspective showing four Phase 1 towers under blue safety mesh on the left and four Phase 2 towers under green safety mesh on the right along the Giong Ong To River.

November 2026 Construction Update: Phase 1 Topping Out and Multi-Tower Vertical Progress

Entering November 2026, construction activity across all eight active towers at The Privé maintains a swift pace. Block 8 completed casting its 32nd floor slab, reaching the highest residential apartment level of the building. The project hosted its official Topping Out Ceremony on Saturday, November 7, 2026 at 08:00 on site. Parallel to structural completions, general contractor Hoa Binh has initiated exterior painting on Block 7, while interior architectural fit-out on Block 8 proceeds sequentially from the third and fourth floors upward.

Seen from across the Giong Ong To River, the eight towers are easy to tell apart by their safety netting. Blue netting wraps Phase 1 (Towers 5 through 8), and green netting covers Phase 2 (Towers 9 through 12). Operational tower cranes and concrete boom pumps are positioned at each tower to hoist reinforcement steel and position formwork.

Tower Height Comparison: October 2026 vs. November 2026

The following table tracks structural floor elevations across all eight active towers, comparing verified heights between October 2026 and November 2026:

Tower October 2026 November 2026 Monthly Progress
Block 8 Floor 31 slab Floor 32 slab +1 floor (Top residential floor; Topped out Nov 7, 2026)
Block 7 Floor 24 slab Floor 27 slab +3 floors (Exterior painting initiated)
Block 6 Floor 23 slab Floor 26 slab +3 floors
Block 5 Floor 24 slab Floor 26 slab +2 floors
Block 12 Floor 16 slab Floor 19 slab +3 floors (Phase 2 lead tower)
Block 9 Floor 14 slab Floor 17 slab +3 floors
Block 10 Floor 12 slab Floor 15 slab +3 floors
Block 11 Floor 9 slab Floor 12 slab +3 floors

Six of the eight active towers added three structural floors during October. Block 8 completed its 32nd floor slab ahead of the Phase 1 topping out ceremony, while Block 5 advanced two floors to reach floor 26.

Phase 1 towers wrapped in blue safety netting rising along the riverbank
Photo: Construction site, late October 2026. Phase 1 towers under blue safety netting rising with active yellow tower cranes beside the Phase 2 green-meshed structures.

Phase 1 Towers under General Contractor Hoa Binh

Phase 1 consists of Towers 5, 6, 7, and 8 constructed by Hoa Binh Construction Group (HBC). On Block 8, floor number signs are fastened directly to the blue safety mesh up to floor 32, providing clear visual confirmation of structural progress from Song Hanh Road. The remaining Phase 1 towers continue vertical construction: Block 7 reached floor 27, while Blocks 5 and 6 reached floor 26. Phase 1 targets an expected delivery in the third quarter of 2027.

Top of Block 8 showing the floor 32 marker and concrete distributor boom
Photo: Construction site, late October 2026. Top of Block 8 displaying the floor 32 elevation marker alongside the concrete placing boom and rooftop crane column.

Phase 2 Vertical Works under Contractor CSCEC

Phase 2 comprises Towers 9, 10, 11, and 12 built by China State Construction Engineering Corporation (CSCEC). Wrapped in green safety netting, these towers utilize aluminum formwork systems to achieve consistent floor cycle times. Block 12 leads the cluster at floor 19, followed by Block 9 at floor 17, Block 10 at floor 15, and Block 11 at floor 12. Handover for Phase 2 is expected in the first quarter of 2028.

Phase 2 towers under green safety netting with aluminum formwork and concrete placing boom
Photo: Construction site, late October 2026. Close-up of Phase 2 tower tops under green netting, showing aluminum formwork assembly and red concrete placing boom operations.

Podium Infrastructure and Landscaped Amenities

At ground level, contractors are advancing basement decks, retail podium slabs, and subsurface infrastructure. Underground power routing and municipal drainage networks are currently being laid. Foundational grading has also commenced for the riverside linear park, which spans nearly one kilometer along the water, as well as the planned resort-style infinity swimming pool complex.

Direct overhead view of the podium deck and basement structures at The Prive
Photo: Construction site, late October 2026. Direct overhead view of the retail podium decks, basement connections, and material logistics zones.
Invitation for The Prive Topping Out Ceremony held on November 7, 2026
Photo: BLUEMARQ invitation. Topping Out Ceremony conducted on Saturday, November 7, 2026 at 08:00 on the project grounds on Song Hanh Road.

October 2026 Construction Update: Floor-by-Floor Rise Across All Eight Towers

Phase 1 Superstructure Elevations: Towers 5, 6, 7, and 8

During October 2026, work across The Privé concentrated on accelerated floor casting for both phases. Block 8 reached its 31st floor slab, positioning itself for topping out. Phase 1 towers 5 and 7 reached the 24th floor, while Tower 6 cast its 23rd floor slab.

The Prive construction site in October 2026 viewed across the Giong Ong To River
Photo: Construction site, October 2026. Panoramic view of all eight rising towers viewed across the Giong Ong To River.

Phase 2 Vertical Casting and Exterior Masonry

In Phase 2, Tower 12 reached the 16th floor, while Tower 9 reached the 14th floor, Tower 10 reached the 12th floor, and Tower 11 reached the 9th floor. Concrete placing booms operated continuously in coordination with mobile concrete batching deliveries. Concurrently, masonry contractors began laying exterior autoclave aerated concrete block walls across floors 10 through 18, immediately following formwork stripping.

Close-up of Block 8 casting the floor 31 slab in October 2026
Photo: Construction site, October 2026. Block 8 casting its 31st floor slab supported by tower crane logistics.
Towers 5 and 7 casting the floor 24 slab viewed from the internal roadway
Photo: Construction site, October 2026. Towers 5 and 7 casting the 24th floor slab viewed from the internal construction road.
Phase 2 tower cluster rising to floor 16 in October 2026
Photo: Construction site, October 2026. Phase 2 towers wrapped in green protective mesh with Block 12 advancing to floor 16.

Construction Milestones

The following table presents verified development milestones for The Privé from initial permits to current field achievements:

Timeline Key Construction and Legal Milestone Status and Source
November 7, 2026 Official Topping Out Ceremony held on site; Block 8 reached floor 32; Block 7 at floor 27; Blocks 5 and 6 at floor 26; Phase 2 towers at floors 12 to 19. Milestone achieved; documented on site by DND Realty.
October 2026 Block 8 reached floor 31; Towers 5 and 7 reached floor 24; Tower 6 reached floor 23; Phase 2 towers reached floors 9 to 16. Completed; confirmed by contractor records.
September 2026 Block 8 completed floor 30; Towers 5 and 7 reached floor 23; Tower 12 reached floor 14. Completed field milestone.
August 2026 Block 8 completed floor 28; Towers 5–7 reached floors 21–22; Towers 9–12 reached floors 6–12. Completed field milestone.
August 7, 2025 HCMC Department of Construction issued Official Document 3126/SXD-PTDT approving 2,093 apartments eligible for future home sales. Statutory sales eligibility certified.
July 23–30, 2025 Completion and formal acceptance of the full basement foundation structure (Minutes 08/NTHTGD and Document 330/KTCN-CD3). Substructure acceptance certified.
September 23, 2024 Official Construction Commencement Notice 69/2024/TBKC/DA issued under Construction Permit 37/GPXD. Statutory commencement recorded.
Q3/2027 (Expected) Phase 1 apartment handover (Towers 5, 6, 7, 8). Expected delivery per developer schedule.
Q1/2028 (Expected) Phase 2 apartment handover (Towers 9, 10, 11, 12). Expected delivery per developer schedule.

Expected Handover Schedule

The handover schedule for The Privé is structured into two distinct operational phases:

  • Phase 1 (Towers 5, 6, 7, and 8): Expected handover in the third quarter of 2027 (Q3/2027).
  • Phase 2 (Towers 9, 10, 11, and 12): Expected handover in the first quarter of 2028 (Q1/2028).

DND Realty notes that the topping out ceremony marks a structural milestone, not readiness for occupancy. Handover requires complete facade weatherproofing, mechanical and electrical testing, elevator certification, fire department inspection approvals, and official municipal sign-offs. Buyers should refer to formal written notices from BLUEMARQ and Dat Xanh Group for binding contractual schedules.

Explore more projects with DND Realty

Frequently Asked Questions

What is the latest construction milestone at The Privé in November 2026?

Lead tower Block 8 cast its 32nd floor slab, its highest residential floor, and the Phase 1 Topping Out Ceremony took place on November 7, 2026. Exterior painting has started on Block 7, while Block 8 has initiated sequential interior fit-out from lower storeys.

When are the Phase 1 and Phase 2 towers expected to be handed over?

Phase 1 (Towers 5, 6, 7, 8) is expected to be handed over in Q3/2027. Phase 2 (Towers 9, 10, 11, 12) is expected in Q1/2028.

Which general contractors are constructing the towers at The Privé?

Phase 1 (Towers 5 through 8) is constructed by Hoa Binh Construction Group (HBC), while Phase 2 (Towers 9 through 12) is built by China State Construction Engineering Corporation (CSCEC).

What core legal permits have been approved for The Privé?

The project holds Construction Permit 37/GPXD issued on September 12, 2024, Sales Permit 3126/SXD-PTDT issued on August 7, 2025 approving 2,093 units, and project completion guarantee facility 207/TB-MB-HCM from Military Commercial Joint Stock Bank (MB).

Where is the sales gallery located and how can overseas buyers consult on the project?

The Sales Gallery is located at 12A Vu Tong Phan, An Phu Ward (Roundabout A12, Vu Tong Phan Street, Binh Trung Ward), open 08:30 to 18:00 daily. DND Realty provides international buyers with remote video site inspections, verified floor plans, and English-speaking advisory services.

Contact DND Realty for International Inquiries

For independent engineering verification, project documentation, or private tour scheduling regarding The Privé, please connect with DND Realty through our direct advisory channels:

Recommendation from DND Realty property experts

The eight towers at The Privé keep moving up floor by floor. Compare the structural milestones on site with the payment schedule in your contract, so you can plan your finances and keep the bank guarantee terms in view.