Imperia Sensa Park Construction Progress – November 2026: Foundation Piling and Ground Infrastructure

By DnD Realty

Content reviewed by Ms Khả Hân, co-founder of DnD Realty with more than 10 years in high-end property.

Key Takeaways
Updated 11/11/2026 · Source: developer progress notices and DND Realty site photos

Aerial surveys from November 2026 confirm that hydraulic pile pressing machines and rotary drilling rigs continue active foundation operations across the leveled site. The central crushed-stone haul road, stockpiles of spun concrete pipe piles, and contractor headquarters are fully established.

  • Project: Imperia Sensa Park (My Phu Residential Area), Vo Chi Cong Street, Phuoc Long B Ward, Thu Duc City, Ho Chi Minh City.
  • Developer: MIK Group (Project legal entity: My Phu Real Estate Investment and Trading Company Limited).
  • Groundbreaking: August 6, 2026; general contractors Ricons and Coteccons; supervision consultant CORE Project Management.
  • Current Status: Continuous operation of hydraulic pile drivers, precast pipe pile stockpiles, and temporary haul roads for foundation works.
  • Development Scale: Approximately 5 hectares (1/500 approved at 4.9 hectares), comprising 2 high-rise apartment towers (922 units) and 93 low-rise residences.
  • Sales and Handover Schedule: Handover expected in the fourth quarter of 2028 (Q4/2028); Sales and Purchase Agreement (SPA) signing expected in Q1/2027; official sales launch scheduled for November 29, 2026.
Updated: November 11, 2026 · Source: MIK Group flycam surveys and official project technical records

Imperia Sensa Park is a master-planned riverside residential community developed by MIK Group along Vo Chi Cong Street in Thu Duc City. Bordered on three sides by the Rach Chiec River, the 5-hectare development integrates two modern residential towers comprising 922 condominiums with 93 exclusive low-rise commercial townhouses and waterfront villas. Following the groundbreaking in August 2026, contractor joint ventures Ricons and Coteccons have pushed forward with ground consolidation, embankment protection, and foundation piling. DND Realty provides this English-language construction report reviewing on-site developments from November 2026 and October 2026. The guide details certified project timelines, expected handover schedules, and key advisory facts for international property investors.

November 2026 Construction Update: Hydraulic Piling Operations and Haul Road Networks

Entering November 2026, the construction site along the Rach Chiec River maintains active heavy mechanical operations across all surveyed sectors. Aerial imagery released by developer MIK Group shows multiple hydraulic pile pressing rigs and rotary drilling units driving foundation piles into the subsoil on November 1, 2026. Site grading has established a uniform working platform across the entire parcel, preparing the ground for the upcoming sales launch on November 29, 2026.

From an elevated perspective, the five-hectare development borders established villa neighborhoods on one side and a natural river inlet on the other. In the background, the arch structure of the Phu Huu Bridge and the regional elevated highway network highlight the strategic connectivity of the waterfront enclave.

Hydraulic Pile Drivers and Concrete Pipe Pile Staging

Along the central parcel alignment, multiple hydraulic pile pressing rigs work simultaneously to sink heavy foundation piles. Adjacent to the active machinery, organized logistics staging yards receive regular shipments of precast centrifugal spun concrete pipe piles arranged in orderly rows ready for placement.

Hydraulic pile pressing rigs and precast pipe pile storage on the construction site in November 2026
Photo: Developer MIK Group, November 1, 2026. Hydraulic pile pressing rigs, stacked precast spun concrete pipe piles, and crushed-stone access corridors serving foundation operations.

Looking toward the Phu Huu Bridge, the synchronized movement of drilling masts and counterweight cranes reflects steady progress across the open riverfront terrain. The development will feature two residential towers rising above landscaped grounds, targeting an expected handover in the fourth quarter of 2028 with verified handover specifications.

Foundation machinery facing Phu Huu bridge at Imperia Sensa Park
Photo: Developer MIK Group, November 1, 2026. Piling equipment and stockpiled foundation piles oriented toward Phu Huu bridge and the elevated roadway.

Crushed-Stone Service Corridors and Waterfront Boundary

A reinforced temporary road surfaced with crushed stone runs through the center of the site. This arterial route connects the entry security checkpoint with active piling sectors and material storage zones, supporting heavy concrete trucks and equipment transporters without damaging the subgrade.

Crushed stone temporary access road across the site in November 2026
Photo: Developer MIK Group, November 1, 2026. Crushed-stone temporary roadway spanning the center of the site, linking foundation sectors and pile storage zones.

Along the project perimeter, a natural water branch provides an ecological buffer separating the private grounds from surrounding urban plots. In one corner of the property, the contractor site headquarters houses project command containers, engineering offices, and safety briefings.

Natural water canal bordering the property in November 2026
Photo: Developer MIK Group, November 1, 2026. Natural canal boundary flanking the development site, with Phu Huu bridge visible in the background.

October 2026 Construction Update: Embankment Protection and Subsurface Infrastructure

During October 2026, site activities achieved significant progress in flood defense and underground civil infrastructure. Construction crews completed the reinforced river dyke embankment along the Rach Chiec River and finished paving internal road D1. Drainage teams also installed underground stormwater culverts, according to field observations on October 21, 2026.

Aerial overview of the Imperia Sensa Park development site in October 2026
Photo: DND Realty site survey flycam, October 21, 2026. Overview of the 5-hectare parcel along the Rach Chiec River with Phu Huu bridge in the distance.

River Embankment Structure and Deep Foundation Preparation

The completed river embankment utilizes corrugated prestressed concrete sheet piles driven deep into the riverbank. This structural retaining barrier stabilizes the shoreline against water erosion and tidal surges, ensuring safe geotechnical conditions for deep basement excavations. Contractors also mobilized multiple self-propelled pile drivers with heavy concrete counterweights for foundation test piling. Technical oversight is managed directly by CORE Project Management.

Self-propelled hydraulic pile drivers and concrete counterweights on site
Photo: DND Realty site survey flycam, October 21, 2026. Self-propelled hydraulic pile drivers alongside stockpiled concrete pipe piles on the graded working platform.

Subsurface Utility Culverts and Ground Grading

Underground utility corridors progressed rapidly throughout October. Deep trenches were excavated to install large-diameter centrifugal reinforced concrete box culverts, establishing separate rainwater and wastewater management channels from the ground up.

Graded internal roads and surveyed ground plots in October 2026
Photo: DND Realty site survey flycam, October 21, 2026. Internal road corridors surfaced with crushed stone and survey grids marked for foundation execution.
Site command container offices and access roads in October 2026
Photo: DND Realty site survey flycam, October 21, 2026. Contractor command container offices and dedicated perimeter haul roads.

Construction Milestones

The following table presents verified development milestones for Imperia Sensa Park from ground breaking to the current status:

Timeline Key Construction Milestone Status and Verification
November 2026 Continuous foundation pile pressing and drilling operations; pipe piles stockpiled across sectors; central crushed-stone haul road active. Active on site; verified via developer flycam photographic records.
October 21, 2026 Mobilization of hydraulic pile drivers; completion of river dyke embankment, road D1, and internal stormwater drainage networks. Completed; documented by DND Realty field survey team.
September 2026 Excavation of underground utility trenches, box culvert installation, and initial pile static load testing. Completed; engineering acceptance records on file.
September 3, 2026 Completion of prestressed corrugated concrete sheet-pile embankment along the Rach Chiec River and Mot Tan Canal. Completed flood-barrier milestone.
August 6, 2026 Official project groundbreaking ceremony, site fencing, and initial site grading. Official commencement milestone reported in national press.
November 29, 2026 Official commercial sales launch event announced by developer MIK Group. Scheduled commercial milestone.
Q1/2027 (Expected) Execution of formal Sales and Purchase Agreements (SPA) upon foundation completion. Expected legal timeline.
Q4/2028 (Expected) Completion of high-rise towers and residential handover to apartment owners. Expected handover timeline per MIK Group kick-off schedule.

Expected Handover Schedule

According to the official project timeline released by developer MIK Group during its corporate presentations, the handover for Imperia Sensa Park is expected in the fourth quarter of 2028 (Q4/2028). The formal signing of Sales and Purchase Agreements (SPA) is planned for the first quarter of 2027 (Q1/2027), following the completion and certification of the foundation and basement structures.

DND Realty notes that all dates remain expected timelines based on current engineering schedules. Foundation piling and basement construction represent critical early milestones that establish long-term structural integrity. Buyers should follow formal written updates and official milestone notifications from MIK Group for legally binding contractual timelines.

Explore more projects with DND Realty

Frequently Asked Questions

What is the current construction status of Imperia Sensa Park in November 2026?

In November 2026, contractors are actively operating hydraulic pile pressing rigs and drilling units across the leveled ground, supported by precast pipe pile stockpiles, crushed-stone internal haul roads, and a completed river dyke embankment.

When did Imperia Sensa Park officially break ground?

Developer MIK Group officially held the project groundbreaking ceremony on August 6, 2026 at the project site on Vo Chi Cong Street, initiating ground preparation and civil works.

What is the function of the completed river embankment?

The corrugated prestressed concrete sheet-pile embankment protects the 5-hectare parcel against riverbank erosion and high tides from the Rach Chiec River, providing a secure perimeter for basement excavation.

When is the official sales launch and expected apartment handover?

The official sales launch is scheduled for November 29, 2026. Sales and Purchase Agreement signing is expected in the first quarter of 2027, with project handover expected in the fourth quarter of 2028.

Where is the show unit located and how can international buyers view the project?

The Imperia Sensa Park Show Unit welcomes visitors at House of MIK, Level 25, Riverfront Financial Centre, 3A-3B Ton Duc Thang, Sai Gon Ward, Ho Chi Minh City. The sales gallery opened on October 31, 2026 and operates daily from 08:30 to 18:00. DND Realty assists international buyers with architectural plans, remote video walkthroughs, and private viewing appointments.

Contact DND Realty for International Inquiries

For independent engineering verification, project documentation, or private tour scheduling regarding Imperia Sensa Park, please connect with DND Realty through our dedicated advisory channels:

Recommendation from DND Realty property experts

Follow the actual progress on site, and check the legal documents and the developer's project management before making any commitment.

Hotline / Zalo: +84 906 873 708
Address: 60 Phan Ba Vanh Street, Thanh My Loi Ward, Ho Chi Minh City
Zalo ZALO +84 906 873 708