Norton Park Construction Progress – November 2026: Foundation Works and Sales Gallery Completion

By DnD Realty
tiến độ căn hộ Norton Park Gamuda Land

Content reviewed by Ms Lê Hiền, co-founder of DnD Realty with more than 10 years in high-end property.

Key Takeaways
Updated 11/11/2026 · Source: developer progress notices and DND Realty site photos

Field surveys from November 2026 record reinforced concrete foundation grids alternating with excavated earth pits across the site. Tower crane CT1 is fully operational, while the exterior of the SkyBridge Sales Gallery at No. 5 Binh Duong Boulevard displays completed glass curtain walls and an architectural entrance portal.

  • Project: Norton Park, No. 5 Binh Duong Boulevard (National Highway 13), Thuan Giao Ward, Ho Chi Minh City (formerly Thuan An City, Binh Duong Province).
  • Developer: Gamuda Land (Project legal entity: Skybridge Real Estate Joint Stock Company / SkyBridge Co., Ltd.).
  • Development Scale: 7.9 hectares, 2 zones comprising 6 residential towers rising 19 storeys with 1 basement level, total 1,286 units.
  • Phase 1 Release: Plot B (Pulse Forest) comprising towers B1, B2, and B3 with 27% construction density across plots B and C.
  • Current Status: Active foundation pit excavation, lean concrete blinding, and rebar grid installation; tower crane CT1 operational; Sales Gallery exterior completed.
  • Expected Handover: September 2029 (09/2029) per Gamuda Land sales schemes; Sales and Purchase Agreement (SPA) signing expected in December 2026.
  • Scale Model Locations: Sales Gallery at No. 5 Binh Duong Boulevard (08:00–20:00 daily) and Gamuda Land Office at Level 15, The METT, Thu Duc City (08:30–17:30 Monday–Sunday).
Updated: November 11, 2026 · Source: DND Realty site survey on November 3, 2026, November 2026 flycam updates, and Gamuda Land technical documentation

Norton Park is a biophilic master-planned condominium community developed by Gamuda Land situated directly on Binh Duong Boulevard (National Highway 13) in Thuan Giao Ward. Spanning 7.9 hectares adjacent to Aeon Mall Canary and opposite Song Be Golf Resort, the development features six 19-storey residential towers offering 1,286 apartments, duplexes, and garden residences. Following the commencement of site preparation in mid-2026, construction on Plot B has advanced through ground stabilization, perimeter Larsen sheet piling, and foundation blinding. DND Realty presents this verified construction progress update examining on-site developments from November 2026 and October 2026. This review details certified project milestones, expected delivery timelines, and essential consultation details for international property buyers.

November 2026 Construction Update: Substructure Works and Sales Gallery Exterior

Entering November 2026, field operations at Norton Park demonstrate clear structural transitions across the 7.9-hectare parcel. Aerial perspectives reveal defined working zones where reinforced concrete foundation slabs alternate with active earth excavation sectors. Heavy construction vehicles navigate dedicated internal haul roads, maintaining a continuous logistics flow alongside the neighboring retail hub.

Norton Park construction progress in November 2026 aerial flycam view of the site and tower crane
Photo: Aerial flycam update, November 2026. Overview of the Norton Park site showing foundation sectors, earthworks, and the operational tower crane next to the commercial mall.

At closer range, the spatial layout of Plot B shows distinct structural divisions. Dedicated internal service paths separate deep foundation pits from gray concrete blinding slabs. Specialized earthmoving machinery and haulage trucks operate within designated corridors, ensuring systematic soil removal and ground consolidation.

Aerial view of Norton Park internal service roadway between excavation zones and concrete slabs
Photo: Aerial flycam update, November 2026. Internal site service roadway running between earth excavation pits and concrete foundation working platforms.

Reinforced Foundation Grids and Operational Tower Crane

From the opposite vantage point, the structural reinforcement network displays clear technical progression. The light gray tones of cured blinding concrete contrast sharply with the surrounding red earth. Tower crane CT1 stands firmly anchored beside reinforced foundation segments and deep excavation trenches, actively hoisting steel rebar bundles and formwork equipment.

Tower crane CT1 alongside reinforced concrete foundation sectors and excavation trenches
Photo: Aerial flycam update, November 2026. Tower crane CT1 and reinforced concrete foundation sections adjacent to active excavation trenches.

A broad diagonal view connects the development parcel with the surrounding urban infrastructure of Thuan Giao Ward. Adjacent to the boundary line, the operating commercial center provides established community conveniences right at the doorstep of the future residential blocks.

Diagonal aerial perspective of Norton Park development parcel beside the commercial center
Photo: Aerial flycam update, November 2026. Diagonal perspective showing the 7.9-hectare parcel layout bordered by commercial and residential facilities.

Sales Gallery Exterior at No. 5 Binh Duong Boulevard

On-site photographic surveys conducted by DND Realty on November 3, 2026 provide an up-close ground perspective of the customer reception facility. Fronting directly onto Binh Duong Boulevard, the SkyBridge Sales Gallery building displays extensive double-height glass curtain walls and an architectural entrance portal finished in bronze-brown tones. Landscaping contractors were recorded finishing sidewalk paving and planting mature trees in front of the main foyer.

Exterior facade of the SkyBridge Sales Gallery at No. 5 Binh Duong Boulevard
Photo: DND Realty site survey, November 3, 2026. Sales Gallery exterior displaying expansive glass curtain walls, brown architectural portal, and sidewalk paving works.

Along the site boundary, a newly paved asphalt roadway borders the green-and-white corrugated construction hoarding. Street lighting poles and greenery run parallel to the perimeter, while the yellow boom of tower crane CT1 rises above the fence line, confirming steady substructure progress within the interior parcel.

Paved perimeter roadway along the construction hoarding at Norton Park
Photo: DND Realty site survey, November 3, 2026. Paved asphalt road alongside the perimeter hoarding, street lighting, and tower crane operating in the background.

October 2026 Construction Update: Larsen Sheet Piling and Blinding Concrete

During October 2026, construction activity at Norton Park centered on geotechnical stabilization, excavation dewatering, and tower crane mobilization. The site established robust protective measures to safeguard deep basement pits during seasonal rains.

Panoramic flycam view of the 7.9-hectare Norton Park site in October 2026
Photo: Aerial flycam, October 2026. Overview of the 7.9-hectare Norton Park site adjacent to Aeon Mall Canary and opposite Song Be Golf Resort.

Basement Pit Stabilization with Larsen Sheet Piles

The primary technical milestone achieved in Plot B was the complete driving of Larsen steel sheet pile walls enclosing the basement excavation pit. This structural barrier prevents soil slippage and groundwater seepage. At the base of the excavation, workers trimmed bored pile heads to design cut-off elevations. Crews then poured lean concrete blinding layers across the pit floor, creating a clean platform for foundation mat rebar assembly.

Deep excavation pit secured with Larsen sheet piles in October 2026
Photo: Construction site, October 2026. Deep foundation pit secured with interlocking Larsen steel sheet piles to maintain site safety.

Lean Concrete Blinding and Tower Crane Installation

Simultaneously, heavy assembly teams erected tower crane CT1, fixed with identification signage from general contractor CBM and developer Gamuda Land. Field inspections on October 23, 2026 confirmed that excavator fleets continued grading the southern sectors while structural glazing on the Sales Gallery reached final placement.

Lean concrete blinding pour and pile head treatment in Plot B
Photo: Construction site, October 2026. Pouring lean concrete blinding and trimming pile heads in the Plot B foundation sector.

Construction Milestones

The following table outlines confirmed construction milestones for Norton Park based on developer disclosures and verified field inspections:

Timeline Verified Milestone Technical Significance
November 2026 Reinforced concrete foundation slabs take shape alongside ongoing excavation; tower crane CT1 operational; Sales Gallery glass facade and entrance portal completed; paved boundary road. Documented across 4 aerial flycam updates and DND Realty site survey on November 3, 2026.
October 23, 2026 Tower crane CT1 active on site with excavator units; Sales Gallery glass curtain wall installed with protective sheeting intact. Verified by DND Realty field inspection.
October 2026 Erection of tower crane; Plot B foundation pit excavated within Larsen sheet piles; pile head trimming and lean concrete blinding poured. Prepares structural working floor for basement foundation mat rebar assembly.
September 21, 2026 Architectural scale model unveiled at Sales Gallery; initial mass excavation and pile static load testing. Ground stabilization and subsoil load-bearing verification.
July 2026 Commencement of SkyBridge Sales Gallery facility construction at No. 5 Binh Duong Boulevard. Establishment of permanent sales and customer consultation infrastructure.
December 2026 (Expected) Execution of formal Sales and Purchase Agreements (SPA). Statutory milestone following municipal foundation acceptance.
September 2029 (Expected) Official project handover to residential apartment owners. Delivery timeline confirmed in official Gamuda Land sales schemes.

Expected Handover Schedule

According to the official sales schemes issued by developer Gamuda Land in October 2026, the expected handover for Norton Park is scheduled for September 2029 (09/2029). The execution of formal Sales and Purchase Agreements (SPA) is planned for December 2026, which corresponds to the completion and statutory certification of the basement foundation structure.

DND Realty reminds prospective purchasers that the handover date is an expected schedule established in the developer payment schemes. Substructure engineering represents the most technically demanding phase of any high-rise building. Buyers should rely on official progress certifications and formal written announcements from Gamuda Land for contractual delivery schedules.

Explore more projects with DND Realty

Frequently Asked Questions

What is the construction progress of Norton Park in November 2026?

In November 2026, Plot B shows reinforced concrete foundation blinding slabs and ongoing excavation, supported by an operational tower crane CT1. The SkyBridge Sales Gallery exterior on Binh Duong Boulevard is completed with large glass walls and entrance portals.

When is the expected handover for Norton Park apartments?

The expected handover for Norton Park is September 2029 (09/2029), with formal Sales and Purchase Agreement (SPA) signing anticipated in December 2026 following foundation structure certification.

What key geotechnical works were completed in October 2026?

October works included driving Larsen steel sheet piling to secure the foundation excavation, chipping bored pile heads to design height, and pouring lean concrete blinding layers across the base of Plot B.

Where can prospective buyers view the Norton Park scale model?

The scale model is available at two locations: the on-site Sales Gallery at No. 5 Binh Duong Boulevard (open 08:00 to 20:00 daily) and the Gamuda Land Office on Level 15, The METT, Thu Duc City (open 08:30 to 17:30 Monday through Sunday).

How does DND Realty support international buyers with Norton Park?

DND Realty offers overseas buyers comprehensive photographic field reports, virtual video walkthroughs, and direct consultation on official pricing starting from 66 million VND per square meter via hotline or WhatsApp.

Contact DND Realty for International Inquiries

International purchasers and overseas investors seeking verified site footage, developer sales policies, or private appointments at the SkyBridge Sales Gallery may connect with DND Realty through our dedicated advisory desk:

Recommendation from DND Realty property experts

Norton Park is at the foundation stage, with handover expected in September 2029. Compare each payment milestone in your contract with the progress on site before every instalment.