Norton Park Construction Progress – November 2026: Foundation Works and Sales Gallery Completion
Content reviewed by Ms Lê Hiền, co-founder of DnD Realty with more than 10 years in high-end property.
Field surveys from November 2026 record reinforced concrete foundation grids alternating with excavated earth pits across the site. Tower crane CT1 is fully operational, while the exterior of the SkyBridge Sales Gallery at No. 5 Binh Duong Boulevard displays completed glass curtain walls and an architectural entrance portal.
- Project: Norton Park, No. 5 Binh Duong Boulevard (National Highway 13), Thuan Giao Ward, Ho Chi Minh City (formerly Thuan An City, Binh Duong Province).
- Developer: Gamuda Land (Project legal entity: Skybridge Real Estate Joint Stock Company / SkyBridge Co., Ltd.).
- Development Scale: 7.9 hectares, 2 zones comprising 6 residential towers rising 19 storeys with 1 basement level, total 1,286 units.
- Phase 1 Release: Plot B (Pulse Forest) comprising towers B1, B2, and B3 with 27% construction density across plots B and C.
- Current Status: Active foundation pit excavation, lean concrete blinding, and rebar grid installation; tower crane CT1 operational; Sales Gallery exterior completed.
- Expected Handover: September 2029 (09/2029) per Gamuda Land sales schemes; Sales and Purchase Agreement (SPA) signing expected in December 2026.
- Scale Model Locations: Sales Gallery at No. 5 Binh Duong Boulevard (08:00–20:00 daily) and Gamuda Land Office at Level 15, The METT, Thu Duc City (08:30–17:30 Monday–Sunday).
Norton Park is a biophilic master-planned condominium community developed by Gamuda Land situated directly on Binh Duong Boulevard (National Highway 13) in Thuan Giao Ward. Spanning 7.9 hectares adjacent to Aeon Mall Canary and opposite Song Be Golf Resort, the development features six 19-storey residential towers offering 1,286 apartments, duplexes, and garden residences. Following the commencement of site preparation in mid-2026, construction on Plot B has advanced through ground stabilization, perimeter Larsen sheet piling, and foundation blinding. DND Realty presents this verified construction progress update examining on-site developments from November 2026 and October 2026. This review details certified project milestones, expected delivery timelines, and essential consultation details for international property buyers.
November 2026 Construction Update: Substructure Works and Sales Gallery Exterior
Entering November 2026, field operations at Norton Park demonstrate clear structural transitions across the 7.9-hectare parcel. Aerial perspectives reveal defined working zones where reinforced concrete foundation slabs alternate with active earth excavation sectors. Heavy construction vehicles navigate dedicated internal haul roads, maintaining a continuous logistics flow alongside the neighboring retail hub.

At closer range, the spatial layout of Plot B shows distinct structural divisions. Dedicated internal service paths separate deep foundation pits from gray concrete blinding slabs. Specialized earthmoving machinery and haulage trucks operate within designated corridors, ensuring systematic soil removal and ground consolidation.

Reinforced Foundation Grids and Operational Tower Crane
From the opposite vantage point, the structural reinforcement network displays clear technical progression. The light gray tones of cured blinding concrete contrast sharply with the surrounding red earth. Tower crane CT1 stands firmly anchored beside reinforced foundation segments and deep excavation trenches, actively hoisting steel rebar bundles and formwork equipment.

A broad diagonal view connects the development parcel with the surrounding urban infrastructure of Thuan Giao Ward. Adjacent to the boundary line, the operating commercial center provides established community conveniences right at the doorstep of the future residential blocks.

Sales Gallery Exterior at No. 5 Binh Duong Boulevard
On-site photographic surveys conducted by DND Realty on November 3, 2026 provide an up-close ground perspective of the customer reception facility. Fronting directly onto Binh Duong Boulevard, the SkyBridge Sales Gallery building displays extensive double-height glass curtain walls and an architectural entrance portal finished in bronze-brown tones. Landscaping contractors were recorded finishing sidewalk paving and planting mature trees in front of the main foyer.

Along the site boundary, a newly paved asphalt roadway borders the green-and-white corrugated construction hoarding. Street lighting poles and greenery run parallel to the perimeter, while the yellow boom of tower crane CT1 rises above the fence line, confirming steady substructure progress within the interior parcel.

October 2026 Construction Update: Larsen Sheet Piling and Blinding Concrete
During October 2026, construction activity at Norton Park centered on geotechnical stabilization, excavation dewatering, and tower crane mobilization. The site established robust protective measures to safeguard deep basement pits during seasonal rains.

Basement Pit Stabilization with Larsen Sheet Piles
The primary technical milestone achieved in Plot B was the complete driving of Larsen steel sheet pile walls enclosing the basement excavation pit. This structural barrier prevents soil slippage and groundwater seepage. At the base of the excavation, workers trimmed bored pile heads to design cut-off elevations. Crews then poured lean concrete blinding layers across the pit floor, creating a clean platform for foundation mat rebar assembly.

Lean Concrete Blinding and Tower Crane Installation
Simultaneously, heavy assembly teams erected tower crane CT1, fixed with identification signage from general contractor CBM and developer Gamuda Land. Field inspections on October 23, 2026 confirmed that excavator fleets continued grading the southern sectors while structural glazing on the Sales Gallery reached final placement.

Construction Milestones
The following table outlines confirmed construction milestones for Norton Park based on developer disclosures and verified field inspections:
| Timeline | Verified Milestone | Technical Significance |
|---|---|---|
| November 2026 | Reinforced concrete foundation slabs take shape alongside ongoing excavation; tower crane CT1 operational; Sales Gallery glass facade and entrance portal completed; paved boundary road. | Documented across 4 aerial flycam updates and DND Realty site survey on November 3, 2026. |
| October 23, 2026 | Tower crane CT1 active on site with excavator units; Sales Gallery glass curtain wall installed with protective sheeting intact. | Verified by DND Realty field inspection. |
| October 2026 | Erection of tower crane; Plot B foundation pit excavated within Larsen sheet piles; pile head trimming and lean concrete blinding poured. | Prepares structural working floor for basement foundation mat rebar assembly. |
| September 21, 2026 | Architectural scale model unveiled at Sales Gallery; initial mass excavation and pile static load testing. | Ground stabilization and subsoil load-bearing verification. |
| July 2026 | Commencement of SkyBridge Sales Gallery facility construction at No. 5 Binh Duong Boulevard. | Establishment of permanent sales and customer consultation infrastructure. |
| December 2026 (Expected) | Execution of formal Sales and Purchase Agreements (SPA). | Statutory milestone following municipal foundation acceptance. |
| September 2029 (Expected) | Official project handover to residential apartment owners. | Delivery timeline confirmed in official Gamuda Land sales schemes. |
Expected Handover Schedule
According to the official sales schemes issued by developer Gamuda Land in October 2026, the expected handover for Norton Park is scheduled for September 2029 (09/2029). The execution of formal Sales and Purchase Agreements (SPA) is planned for December 2026, which corresponds to the completion and statutory certification of the basement foundation structure.
DND Realty reminds prospective purchasers that the handover date is an expected schedule established in the developer payment schemes. Substructure engineering represents the most technically demanding phase of any high-rise building. Buyers should rely on official progress certifications and formal written announcements from Gamuda Land for contractual delivery schedules.
Explore more projects with DND Realty
Updated 23.10.2026Norton Park Project Overview & Master Plan了解胡志明市Norton Park公寓的项目位置、户型及付款安排。项目由Gamuda Land开发,占地7.9公顷,售价每平方米6,600万越南盾起,按标准方案折后价计算,未含增值税。查看交房计划、法律文件及沙盘参观信息,联系DND Realty获取开发商正式资料。Read in Vietnamese
Updated 11.11.2026Eaton Park by Gamuda LandEaton Park foreign buyer guide: 3.7 hectares, six towers, 1,968 apartments, ownership notes, legal documents and construction progress. DND Realty 0906.873.708.Read in Vietnamese
Updated 26.10.2026Elysian by Gamuda LandElysian Gamuda Land at 170 Lo Lu, Long Phuoc Ward, HCMC: 4 towers of 21 storeys, 1,322 units, 2027 expected handover. Prices, progress and legal files.Read in Vietnamese
Updated 11.11.2026Gladia Heights Project OverviewGladia Heights by Keppel Land & Khang Dien: 3 towers of 15 storeys, 616 units, Vo Chi Cong corridor. Prices from VND 83M/m². Hotline +84 906 873 708.Read in Vietnamese
Updated 13.11.2026East HCMC Multi-Project ReviewCompare Eaton Park, Gladia Heights and The Privé: 2027-2028 handover schedules, site progress, legal documents and payment terms from DND Realty.Read in Vietnamese Frequently Asked Questions
What is the construction progress of Norton Park in November 2026?
In November 2026, Plot B shows reinforced concrete foundation blinding slabs and ongoing excavation, supported by an operational tower crane CT1. The SkyBridge Sales Gallery exterior on Binh Duong Boulevard is completed with large glass walls and entrance portals.
When is the expected handover for Norton Park apartments?
The expected handover for Norton Park is September 2029 (09/2029), with formal Sales and Purchase Agreement (SPA) signing anticipated in December 2026 following foundation structure certification.
What key geotechnical works were completed in October 2026?
October works included driving Larsen steel sheet piling to secure the foundation excavation, chipping bored pile heads to design height, and pouring lean concrete blinding layers across the base of Plot B.
Where can prospective buyers view the Norton Park scale model?
The scale model is available at two locations: the on-site Sales Gallery at No. 5 Binh Duong Boulevard (open 08:00 to 20:00 daily) and the Gamuda Land Office on Level 15, The METT, Thu Duc City (open 08:30 to 17:30 Monday through Sunday).
How does DND Realty support international buyers with Norton Park?
DND Realty offers overseas buyers comprehensive photographic field reports, virtual video walkthroughs, and direct consultation on official pricing starting from 66 million VND per square meter via hotline or WhatsApp.
Contact DND Realty for International Inquiries
International purchasers and overseas investors seeking verified site footage, developer sales policies, or private appointments at the SkyBridge Sales Gallery may connect with DND Realty through our dedicated advisory desk:
- Direct International Line (WhatsApp & Zalo): (+84) 0906.873.708
- Investor Advisory Email: info@dndrealty.com.vn
- Central Operations Office: 60 Phan Ba Vanh, Thanh My Loi Ward, Thu Duc City, Ho Chi Minh City, Vietnam
- Online Portal: dndrealty.com.vn
- Project Overview (EN): Norton Park Gamuda Land Project Overview