IKI Village Construction Progress – November 2026: Vitalis Tower Foundation Concreting
Content reviewed by Ms Khả Hân, co-founder of DnD Realty with more than 10 years in high-end property.
IKI Village Construction Progress – November 2026: Vitalis Tower Foundation Concreting
IKI Village construction in November 2026 reached a major structural milestone with the completion of foundation cap concreting for the Vitalis tower on November 09, 2026. The 5.1-hectare project along Ring Road 3 operates two active tower cranes while progressing through basement substructure works toward an expected handover on June 25, 2028.
- Developer: An Khai Hung Investment Joint Stock Company.
- Location: Ring Road 3 frontage and Lo Lu extension, Long Phuoc Ward, Ho Chi Minh City.
- Scale: 5.1 hectares (project site 41,344 sqm), 2 residential towers comprising Vitalis (30 storeys, 313 units) and Harmonie (24 storeys, 111 units), totaling 424 apartments and up to 2 basements.
- Latest Structural Status: Vitalis tower foundation cap concrete pouring executed overnight on November 09, 2026; 2 operational tower cranes and robust steel shoring system.
- Expected Handover: Expected June 25, 2028 (Q2/2028) based on the developer payment schedule.
November 2026 update: foundation concrete pouring at Vitalis tower
During the night of November 09, 2026, the construction site completed a continuous concrete pour for the CC2 foundation cap of the Vitalis tower. Overnight placement maintained uninterrupted material flow and optimal concrete binding conditions. General contractor Phuoc Thanh executed the pour under the direct engineering supervision of Core Asia.
Overnight foundation concrete placement on November 09, 2026
Concrete boom pumps commenced pumping at 23:00 on November 09 and finished at 03:00 on the morning of November 10, 2026. The 4-hour operation proceeded under high-powered site floodlights. Representatives from An Khai Hung, Core Asia, and Phuoc Thanh remained on site throughout to verify concrete slump, material temperatures, and structural compliance.

Direct discharge pipes distributed ready-mixed concrete evenly across the reinforced foundation mesh. Engineers conducted slump tests on incoming concrete mixer trucks to confirm structural specifications before placement.


Excavation pit shoring and reinforcement rebar structure
The foundation pit for Vitalis tower is stabilized by a perimeter diaphragm wall paired with heavy structural steel shoring. Diagonal steel struts and vertical kingposts are anchored around the pit perimeter to secure the excavation embankments against lateral soil pressure.

At the base of the excavation, workers tied high-density steel rebar mats for the foundation pad. Steel walkways above the pit enable engineers to review blueprints and inspect reinforcement density before concrete casting.

Site panoramic view along the Ring Road 3 corridor
The IKI Village site is prominent with two tall tower cranes operating adjacent to the elevated Ring Road 3 viaduct. The elevated highway forms the western boundary of the project land in Long Phuoc Ward. Safety warning signs and access protocols are posted along the main construction entrance.

From the elevated corridor, the open foundation excavation reveals the perimeter diaphragm wall and base reinforcement grid. The project provides new residential supply for the eastern sector of Ho Chi Minh City, with clear road connectivity toward the High-Tech Park.

Construction milestones of IKI Village
The project follows an organized construction timeline from initial groundbreaking through to building completion:
| MILESTONE DATE | CONSTRUCTION WORK ON SITE | STATUS |
|---|---|---|
| April 17, 2026 | Official project groundbreaking; bored piling works initiated by Bachy Soletanche. | Completed |
| October 03, 2026 | Official project sales launch and execution of initial Sale and Purchase Agreements (SPA). | Completed |
| November 09–10, 2026 | Overnight concrete pouring of CC2 foundation cap for Vitalis tower by Phuoc Thanh under Core Asia supervision. | Completed |
| November 25, 2026 (Expected) | Completion of basement base slab (Stage 2 payment installment milestone). | Scheduled Target |
| January 25, 2027 (Expected) | Basement top slab closure (Stage 3 payment installment milestone). | Scheduled Target |
| December 25, 2027 (Expected) | Structural concrete topping out of residential towers (Stage 11 payment installment milestone). | Future Target |
| June 25, 2028 (Expected) | Official apartment handover to buyers (Q2/2028) with finished landscape gardens. | Scheduled Target |
Expected handover schedule and payment milestones
Developer An Khai Hung targets building completion and apartment handover on June 25, 2028 (Q2/2028). Finished apartments will be delivered with private landscaped gardens designed by Belt Collins, complete built-in kitchen cabinetry, and fitted bathroom fixtures.
The standard payment plan comprises 18 construction-linked installments. Following the initial 7% contract signing installment, Stage 2 requires 7% upon basement bottom completion on November 25, 2026. Stage 3 requires 7% upon basement ceiling closure on January 25, 2027. Buyers should cross-check verified site progress reports before disbursing scheduled installments.
Explore more projects with DND Realty
Updated 26.10.2026Elysian Lò Lu Project ProfileElysian Gamuda Land at 170 Lo Lu, Long Phuoc Ward, HCMC: 4 towers of 21 storeys, 1,322 units, 2027 expected handover. Prices, progress and legal files.Read in Vietnamese
Updated 11.11.2026Eaton Park Gamuda Land Project GuideEaton Park foreign buyer guide: 3.7 hectares, six towers, 1,968 apartments, ownership notes, legal documents and construction progress. DND Realty 0906.873.708.Read in Vietnamese
Updated 11.11.2026Gladia Heights Keppel Khang Dien OverviewGladia Heights by Keppel Land & Khang Dien: 3 towers of 15 storeys, 616 units, Vo Chi Cong corridor. Prices from VND 83M/m². Hotline +84 906 873 708.Read in Vietnamese
Updated 20.11.2026The Prive Bluemarq Project ProfileRead in Vietnamese
Updated 09.11.2026Elysian vs Eaton Park ComparisonCompare Elysian and Eaton Park by Gamuda Land across location, scale, Biophilic design, handover schedule and unit prices of 72 million vs 144 million VND/m².Read in Vietnamese
Updated 13.11.2026Eaton Park vs Gladia Heights vs The Prive AnalysisCompare Eaton Park, Gladia Heights and The Privé: 2027-2028 handover schedules, site progress, legal documents and payment terms from DND Realty.Read in Vietnamese Frequently asked questions about IKI Village progress
What is the latest construction milestone at IKI Village in November 2026?
On the night of November 09, 2026, the construction team completed continuous concrete pouring for the CC2 foundation cap of Vitalis tower, operating from 23:00 to 03:00 under direct engineering supervision.
Which contractors are responsible for building and supervising IKI Village?
General contractor Phuoc Thành leads structural building works, Core Asia serves as quality supervision consultant, and Bachy Soletanche executed the foundation piling package.
What is the expected handover schedule for IKI Village apartments?
According to developer payment schedules, apartment handovers are projected for June 25, 2028 (Q2/2028), including completed private gardens designed by Belt Collins.
Where is the IKI Village sales gallery and model apartment located?
The IKI Gallery is located at 675 Do Xuan Hop, Phuoc Long Ward, Ho Chi Minh City, displaying the Sky Villa Residences model apartment with high-ceiling living space and private garden layouts.
How can international buyers inspect construction progress and project documentation?
DND Realty assists foreign buyers with digital site photos, contractor logs, and legal document reviews, including Decision 5252, Decision 1582, and Decision 2844 via direct hotline consultation.
Connect with DND Realty for project consultations
DND Realty monitors construction progress and municipal planning updates along Ring Road 3. International purchasers seeking site inspection files or payment schedule advisory can contact our dedicated multilingual team.