Eaton Park Construction Progress – November 2026: Facade Netting Removal and Arrival Infrastructure
Content reviewed by Ms Khả Hân, co-founder of DnD Realty with more than 10 years in high-end property.
Eaton Park completed structural work on all six towers following the topping out of Cove and Lagoon on August 12, 2026. Construction began in March 2024. Phase 1 towers A5 and A6 have an expected handover in the second quarter of 2027, while towers A1, A2, A3, and A4 have an expected handover in the first quarter of 2028.
- Developer: Gamuda Land (Malaysia).
- Location: 63 Mai Chi Tho Boulevard, An Phu Ward (now Binh Trung Ward), Thu Duc City, Ho Chi Minh City.
- Scale: 3.76 hectares, 6 residential towers.
- Structural Milestone: All 6 towers reached structural completion on August 12, 2026.
- November 2026 Status: Protective netting removed on select towers exposing curved balconies; remaining towers continue upper-level work under safety mesh; arrival entrance paved with stone and planter boxes.
- Expected Handover: Towers A5 (Grove) and A6 (Strait) expected in Q2/2027; Towers A1 (Alpine), A2 (Forest), A3 (Cove), and A4 (Lagoon) expected in Q1/2028.
Eaton Park is a master-planned residential development by Gamuda Land situated along Mai Chi Tho Boulevard in Thu Duc City. Covering 3.76 hectares, the project comprises six residential towers ranging from 29 to 39 storeys with 2,052 apartments, penthouses, and commercial retail units. All six towers completed their structural concrete frames in August 2026. Construction is now advancing into exterior and interior finishing. DND Realty provides this reverse-chronological field update covering on-site developments from November 2026 and October 2026. The report includes documented construction milestones, expected handover timelines, and essential guidance for international property buyers.

November 2026 Construction Update: Facade Netting Removal and Arrival Infrastructure
Entering November 2026, the Eaton Park construction site along Mai Chi Tho Boulevard maintains steady architectural finishing work. Following the full structural completion of all six towers in August, on-site contractors have focused on exterior treatments, window glazing, and ground-level civil works. In late October 2026, developer Gamuda Land released its construction update confirming on-track delivery goals alongside systematic technical inspections. For buyers tracking their future residences, the progressive removal of protective exterior netting offers a direct look at the finished building envelopes, while permanent ground-level landscaping continues to take shape.
Exterior Facades and Curved Balcony Systems
On towers where heavy structural tasks have concluded, workers have begun dismantling the exterior safety netting. Close-up observations indicate that the wave-like curved balconies now display their final exterior paint coating. Aluminum window frames and architectural glass panels are installed in uniform alignment across the lower and middle residential levels.

When viewed through the roadside greenery bordering the site, the unmeshed tower facades present an open architectural profile. This visible exterior completion allows owners to verify the finished construction against the original architectural renderings. However, DND Realty notes that external envelope completion represents one specific phase of construction. Mechanical, electrical, plumbing (MEP), and interior fit-out tasks require independent technical sign-offs before formal handover inspections begin.

Upper-Level Construction on Meshed Towers and Site Infrastructure
Parallel to the unmeshed sections, the site maintains standard safety netting across several towers undergoing active upper-level facade treatments. Two towers remain wrapped in blue mesh, while adjoining buildings are cloaked in green mesh with yellow tower cranes operating at rooftop height to hoist building materials.

At ground level, civil works demonstrate concrete progress on arrival infrastructure. The main entrance boulevard has been paved with cut stone, accompanied by concrete tree planter boxes and an arrival canopy featuring the project insignia. On-site technical teams in high-visibility vests conduct routine field surveys to monitor structural tolerances and civil quality standards across the podium levels.

October 2026 Construction Update: Facade Glass Installation and Commercial Podium
During October 2026, construction activity at Eaton Park concentrated on exterior glazing installations, safety mesh maintenance, and commercial podium assembly. Following the topping out of all six towers in August 2026, the site shifted from structural framework building to facade completion across all phases.

Retail Podium Structure and Balcony Glazing
Site surveys conducted on October 11, 2026 recorded steady progress along the lower commercial levels. The architectural curved roof of the retail podium reached exterior structural completion, backed by prominent white lettering spelling Eaton Park set within a planted green zone. Glazing teams installed balcony railings and window assemblies on multiple mid-level storeys while tower cranes continued lifting materials to the upper mechanical levels.

Six-Tower Skyline Alignment and Rooftop Crown Profiles
Aerial flycam imagery published by Gamuda Land in October 2026 displayed the entire six-tower arrangement against the skyline. Towers A1 and A2 showed advanced facade glazing, while adjoining towers carried developer identification banners on their green and blue netting. Rooftop crown frames were visible across several towers, alongside early shaping of podium-level landscaped gardens.

Construction Milestones
The following table presents verified development milestones for Eaton Park from project inception to current field records:
| Timeline | Verified Milestone | Information Source and Scope |
|---|---|---|
| November 2026 | Protective netting removed on select towers exposing curved balconies; remaining towers maintain safety mesh for upper-floor work; entrance boulevard stone paving and planter boxes installed. | DND Realty on-site survey photographs, November 2026. Visual field record; does not substitute interior acceptance files. |
| October 11, 2026 | Commercial podium curved roof exterior assembled with project signage in place; multiple residential storeys fitted with window glass and balcony railings; tower cranes active. | DND Realty on-site photography, October 11, 2026. Visual progress check. |
| September 23, 2026 | Towers A1 and A2 completed exterior facade work; Towers A3 and A4 conducted exterior finishing; podium landscape preparation active. | DND Realty field survey record, September 23, 2026. |
| August 12, 2026 | Official topping out ceremony for final towers A3 (Cove) and A4 (Lagoon); structural framework completed across all 6 towers. | Gamuda Land announcement and Phap Luat Newspaper coverage, August 13–14, 2026. |
| March 2024 | Official project groundbreaking. | Gamuda Land corporate announcements. |
| Q2/2027 – Q1/2028 (Expected) | Towers A5 (Grove) and A6 (Strait) expected in Q2/2027; Towers A1 (Alpine), A2 (Forest), A3 (Cove), and A4 (Lagoon) expected in Q1/2028. | Recorded by DND Realty from project field documentation, October 2026. |
Expected Handover Schedule
The handover schedule for Eaton Park is organized by development phases with specific expected timelines:
- Phase 1 (Towers A5 Grove and A6 Strait): Expected handover in the second quarter of 2027 (Q2/2027).
- Phase 2 and Phase 3 (Towers A1 Alpine, A2 Forest, A3 Cove, and A4 Lagoon): Expected handover in the first quarter of 2028 (Q1/2028).
DND Realty emphasizes that these handover dates remain expected timelines based on on-site observations recorded in October 2026. Exterior architectural completion represents a visible milestone, but it does not equal handover readiness. Apartment handovers require comprehensive testing of electrical systems, plumbing, fire protection systems, and municipal occupancy approvals. Buyers should rely on official written handover notices from Gamuda Land for binding contractual dates.
Explore more projects with DND Realty
Updated 11.11.2026Eaton Park Project Overview & Master PlanEaton Park foreign buyer guide: 3.7 hectares, six towers, 1,968 apartments, ownership notes, legal documents and construction progress. DND Realty 0906.873.708.Read in Vietnamese
Updated 29.10.2026Eaton Park vs The PrivéCompare Eaton Park and The Privé in An Phu across 10 technical and financial criteria: Mai Chi Tho frontage vs Nam Rach Chiec peninsula, 2026 prices, Q2-Q3/2027 handover and pay…Read in Vietnamese
Updated 09.11.2026Elysian vs Eaton ParkCompare Elysian and Eaton Park by Gamuda Land across location, scale, Biophilic design, handover schedule and unit prices of 72 million vs 144 million VND/m².Read in Vietnamese
Updated 13.11.2026Eaton Park, Gladia Heights, and The PrivéCompare Eaton Park, Gladia Heights and The Privé: 2027-2028 handover schedules, site progress, legal documents and payment terms from DND Realty.Read in Vietnamese
Updated 14.11.2026Palm River vs Eaton ParkPalm River vs Eaton Park in East HCMC: compare riverfront and Mai Chi Tho locations, prices from 125-150 million VND/m², legal files, and 2027 handover.Read in Vietnamese Frequently Asked Questions
Have all six towers at Eaton Park completed structural topping out?
Yes. Gamuda Land and general contractor Coteccons conducted the topping out ceremony for towers A3 Cove and A4 Lagoon on August 12, 2026, confirming that all six towers have reached their full structural concrete height.
What is the current construction status of Eaton Park in November 2026?
In November 2026, several towers have removed exterior protective netting to reveal curved balconies and finished paintwork, while other towers continue facade glazing under safety mesh. Ground-level work includes stone paving and landscaping along the main arrival boulevard.
When is the expected handover for Eaton Park apartments?
Handover is expected in the second quarter of 2027 for Towers A5 Grove and A6 Strait, and in the first quarter of 2028 for Towers A1 Alpine, A2 Forest, A3 Cove, and A4 Lagoon.
Can prospective buyers visit the show units on site?
On-site apartment show units are discontinued. However, the Eaton Park Experience Gallery on the first floor at 63 Mai Chi Tho Boulevard is open from 08:30 to 17:30 Monday through Sunday for architectural scale model viewings and project consultations.
How does DND Realty assist overseas buyers tracking Eaton Park?
DND Realty provides remote international buyers with monthly high-definition photo and video documentation, virtual walkthrough consultations, and direct English-language verification of construction milestones via hotline or WhatsApp.
Contact DND Realty for International Inquiries
For independent property consultations, updated construction media, or project documents regarding Eaton Park, please contact DND Realty through our dedicated advisory channels:
- Hotline / WhatsApp / Zalo: (+84) 0906.873.708
- Email: info@dndrealty.com.vn
- Head Office: 60 Phan Ba Vanh, Thanh My Loi Ward, Thu Duc City, Ho Chi Minh City, Vietnam
- Website: dndrealty.com.vn
- Project Overview (EN): Eaton Park Gamuda Land Project Overview