Project news

Gladia Heights Construction Progress – November 2026: Tower B3 Floor 4 Structural Works

By DnD Realty
Toàn cảnh công trường dự án Gladia Heights tháng 9/2026 nhìn từ trên cao

Content reviewed by Ms Khả Hân, co-founder of DnD Realty with more than 10 years in high-end property.

Gladia Heights Construction Progress – November 2026: Tower B3 Floor 4 Structural Works

Gladia Heights construction in November 2026 is progressing rapidly as Tower B3 completed its 4th floor slab and prepares for the 5th floor. All three 15-storey towers have finished their commercial podiums and operate three yellow Potain cranes. Apartment handover remains projected for the fourth quarter of 2027 under developer planning.

Key Takeaways
Updated 12/11/2026 · Source: Keppel, Khang Dien announcements and DND Realty site survey
  • Developer: Doan Nguyen Real Estate Investment and Trading Company Limited (Joint venture of Keppel Group and Khang Dien).
  • Location: Vo Chi Cong Road, Binh Trung Ward (formerly Binh Trung Dong Ward), Ho Chi Minh City.
  • Scale: 1.26 hectares (within the 11.8-hectare master plan), 3 towers rising 15 storeys: Tower B1 (The Future), Tower B2 (The First), Tower B3 (The Advanta), comprising 616 apartments and 23 retail units.
  • Latest Structural Status: Tower B3 completed 4th floor slab; three Potain cranes operational; ground clearing underway for low-rise resident Clubhouse.
  • Expected Handover: Expected in the fourth quarter of 2027 (Q4/2027) as announced on site billboards.

November 2026 update: Tower B3 completes 4th floor slab and clubhouse land clearing

Site observations in early November 2026 demonstrate clear structural advancement across the Gladia Heights development. General contractor An Phong Construction continues vertical construction on all three residential blocks. Tower B3 (The Advanta) leads site progress, having completed structural concrete for the 4th floor.

Tower B3 structural progress and site observations

From the Vo Chi Cong corridor, all three towers stand wrapped in dark green safety netting. Three yellow Potain tower cranes operate in coordination to lift structural rebar and formwork to upper working decks. Ground-level columns are fully cast, defining the structural perimeter of the lower retail podium.

Aerial flycam view of Gladia Heights construction progress with 3 towers and cranes in November 2026
Photo: DND Realty site visit, early November 2026: Aerial view of the three towers wrapped in green protective netting with three yellow cranes along Vo Chi Cong avenue.

Close inspection behind perimeter hoardings shows dense scaffolding supporting active working levels. Starter rebar bars extend vertically above the 4th floor slab of Tower B3, preparing for column casting toward the 5th floor. Billboard graphics displaying the Future First theme border the exterior property boundary.

Tower structure with safety netting and concrete columns behind billboard hoarding
Photo: DND Realty site visit, early November 2026: Tower structure with safety netting and reinforced concrete ground-floor columns behind billboard hoarding.
Close-up of active construction floors showing starter rebar bars above slab level
Photo: DND Realty site visit, early November 2026: Close-up of active construction floors showing starter rebar bars rising above the upper slab level.

Internal infrastructure and clubhouse land clearing

Paved internal access avenues have been cleared to facilitate heavy supply delivery. Adjacent to the Sales Gallery, bulldozers are leveling ground for the low-rise resident Clubhouse. Furthermore, the 30-hectare expansion parcel has completed tree clearance and riverbank widening in preparation for the High-Rise 2 phase.

Tower cluster and yellow cranes viewed from internal road junction
Photo: DND Realty site visit, early November 2026: Tower cluster and yellow cranes viewed from the internal road junction.

The road intersection includes a newly positioned power substation to serve project utilities. The front elevation of the residential towers continues upward above surrounding trees, presenting an organized building site along the internal avenue.

Front elevation of the tower wrapped in dark green mesh rising steadily
Photo: DND Realty site visit, early November 2026: Front elevation of the tower wrapped in dark green mesh rising steadily along the internal access avenue.

October 2026 update: retail podium completion and mid-month floor pouring

Site progress during October 2026 marked the transition from lower substructure works to standard floor cycles. In early October, the concrete commercial podium structure reached completion across all three towers, allowing full installation of exterior safety mesh.

Mid-October milestone pouring and podium completion

By mid-October 2026, contractor An Phong commenced continuous slab pouring on upper levels. Tower B3 poured its 3rd floor slab while Tower B2 commenced pouring its 2nd floor slab. Construction crews maintained steady progress across day and night shifts.

Tower B2 in foreground and Tower B3 in background pouring 3rd floor slab
Photo: DND Realty site visit, October 17, 2026: Tower B2 in foreground and Tower B3 in background pouring 3rd floor slab.

At Tower B1 (The Future), dense scaffolding and perimeter sheet piling surrounded deep excavation pits. The successful completion of the commercial podiums established an expansive structural base across the 1.26-hectare footprint.

Overview of all three Gladia Heights towers with completed retail podium structure
Photo: DND Realty site visit, early October 2026: Overview of all three Gladia Heights towers with completed retail podium structure.

Construction milestones of Gladia Heights

The cumulative construction progress of Gladia Heights is documented in the following chronological milestone table:

MILESTONE DATE CONSTRUCTION WORK ON SITE STATUS
January 2026 Project groundbreaking and commencement of apartment substructure works. Completed
June 12, 2026 Official project introduction by Keppel Land and Khang Dien. Completed
July 23, 2026 Department of Construction issued Official Letter 26381/SXD-PTDT approving future housing sales eligibility. Completed
September 2026 Substructure completed for Towers B2 and B3; installation of 3 Potain tower cranes. Completed
Early October 2026 Retail podium structure completed; green mesh installed; all 3 towers reached 1st floor. Completed
Mid October 2026 Tower B3 poured 3rd floor slab; Tower B2 poured 2nd floor slab under continuous shifts. Completed
Early November 2026 Tower B3 completed 4th floor slab; site clearing for low-rise Clubhouse and 30-ha expansion parcel. Ongoing
Q4/2027 (Expected) Projected apartment handover to homeowners as announced on site billboards. Scheduled Target
2028 (Expected) Anticipated processing and issuance of official ownership certificates (pink books). Future Target

Expected handover schedule and inspection advice

Site billboards at Gladia Heights indicate an expected apartment handover in the fourth quarter of 2027 (Q4/2027). The project possesses key statutory documentation, including Official Letter 26381/SXD-PTDT and Land Use Certificates DQ 128066 and DQ 128067 issued in November 2024.

Prospective purchasers should review the formal payment schedules published by Keppel and Khang Dien. Payment plans feature stages tied directly to verified construction milestones. When reviewing options, buyers are advised to request official contractor milestone reports for their specific tower rather than relying solely on overall site photos.

Explore more projects with DND Realty

Frequently asked questions about Gladia Heights progress

What is the current construction status of Gladia Heights in November 2026?

In early November 2026, Tower B3 completed its 4th floor slab and prepares for the 5th floor. All 3 towers have finished retail podiums and are covered in green safety netting, with 3 Potain cranes operating.

Who is the general contractor and developer of Gladia Heights?

The developer is Doan Nguyen Real Estate Investment and Trading Company Limited, a joint venture between Keppel and Khang Dien. An Phong Construction serves as general contractor.

How many towers make up Gladia Heights and what are their official names?

Gladia Heights comprises 3 towers rising 15 storeys: Tower B1 (The Future), Tower B2 (The First), and Tower B3 (The Advanta), providing 616 luxury apartments and 23 retail units.

Where is the Gladia Heights show unit located and what are the visiting hours?

Show units opened on June 14, 2026, and welcome visitors daily from 08:30 to 17:30 at the project sales gallery along Vo Chi Cong Road, Binh Trung Ward.

When is Gladia Heights expected to be handed over to buyers?

Site billboards announce an expected handover in the fourth quarter of 2027 (Q4/2027), subject to formal milestone notices from Keppel and Khang Dien.

How does DND Realty assist foreign property buyers with project inspections?

DND Realty arranges guided site visits, provides aerial flycam footage, and assists foreign buyers with verified legal documents and SPA registration procedures.

Consult with DND Realty property advisors

DND Realty provides ongoing field monitoring of real estate developments in East Ho Chi Minh City. International buyers seeking project documents or virtual site viewings are invited to contact our team.

DND Realty International Advisory Desk

Superstructure works at Gladia Heights are rising steadily on Vo Chi Cong Road. Connect with our multilingual team to access monthly progress photos, architectural floor plans, and developer payment guidelines.

Hotline / WhatsApp / Zalo: +84 906 873 708
Office Address: 60 Phan Ba Vanh, Thanh My Loi Ward, Ho Chi Minh City
English Project Hub: Gladia Heights English Guide

Zalo ZALO +84 906 873 708