Gladia Heights Construction Progress – November 2026: Tower B3 Floor 4 Structural Works
Content reviewed by Ms Khả Hân, co-founder of DnD Realty with more than 10 years in high-end property.
Gladia Heights Construction Progress – November 2026: Tower B3 Floor 4 Structural Works
Gladia Heights construction in November 2026 is progressing rapidly as Tower B3 completed its 4th floor slab and prepares for the 5th floor. All three 15-storey towers have finished their commercial podiums and operate three yellow Potain cranes. Apartment handover remains projected for the fourth quarter of 2027 under developer planning.
- Developer: Doan Nguyen Real Estate Investment and Trading Company Limited (Joint venture of Keppel Group and Khang Dien).
- Location: Vo Chi Cong Road, Binh Trung Ward (formerly Binh Trung Dong Ward), Ho Chi Minh City.
- Scale: 1.26 hectares (within the 11.8-hectare master plan), 3 towers rising 15 storeys: Tower B1 (The Future), Tower B2 (The First), Tower B3 (The Advanta), comprising 616 apartments and 23 retail units.
- Latest Structural Status: Tower B3 completed 4th floor slab; three Potain cranes operational; ground clearing underway for low-rise resident Clubhouse.
- Expected Handover: Expected in the fourth quarter of 2027 (Q4/2027) as announced on site billboards.
November 2026 update: Tower B3 completes 4th floor slab and clubhouse land clearing
Site observations in early November 2026 demonstrate clear structural advancement across the Gladia Heights development. General contractor An Phong Construction continues vertical construction on all three residential blocks. Tower B3 (The Advanta) leads site progress, having completed structural concrete for the 4th floor.
Tower B3 structural progress and site observations
From the Vo Chi Cong corridor, all three towers stand wrapped in dark green safety netting. Three yellow Potain tower cranes operate in coordination to lift structural rebar and formwork to upper working decks. Ground-level columns are fully cast, defining the structural perimeter of the lower retail podium.

Close inspection behind perimeter hoardings shows dense scaffolding supporting active working levels. Starter rebar bars extend vertically above the 4th floor slab of Tower B3, preparing for column casting toward the 5th floor. Billboard graphics displaying the Future First theme border the exterior property boundary.


Internal infrastructure and clubhouse land clearing
Paved internal access avenues have been cleared to facilitate heavy supply delivery. Adjacent to the Sales Gallery, bulldozers are leveling ground for the low-rise resident Clubhouse. Furthermore, the 30-hectare expansion parcel has completed tree clearance and riverbank widening in preparation for the High-Rise 2 phase.

The road intersection includes a newly positioned power substation to serve project utilities. The front elevation of the residential towers continues upward above surrounding trees, presenting an organized building site along the internal avenue.

October 2026 update: retail podium completion and mid-month floor pouring
Site progress during October 2026 marked the transition from lower substructure works to standard floor cycles. In early October, the concrete commercial podium structure reached completion across all three towers, allowing full installation of exterior safety mesh.
Mid-October milestone pouring and podium completion
By mid-October 2026, contractor An Phong commenced continuous slab pouring on upper levels. Tower B3 poured its 3rd floor slab while Tower B2 commenced pouring its 2nd floor slab. Construction crews maintained steady progress across day and night shifts.

At Tower B1 (The Future), dense scaffolding and perimeter sheet piling surrounded deep excavation pits. The successful completion of the commercial podiums established an expansive structural base across the 1.26-hectare footprint.

Construction milestones of Gladia Heights
The cumulative construction progress of Gladia Heights is documented in the following chronological milestone table:
| MILESTONE DATE | CONSTRUCTION WORK ON SITE | STATUS |
|---|---|---|
| January 2026 | Project groundbreaking and commencement of apartment substructure works. | Completed |
| June 12, 2026 | Official project introduction by Keppel Land and Khang Dien. | Completed |
| July 23, 2026 | Department of Construction issued Official Letter 26381/SXD-PTDT approving future housing sales eligibility. | Completed |
| September 2026 | Substructure completed for Towers B2 and B3; installation of 3 Potain tower cranes. | Completed |
| Early October 2026 | Retail podium structure completed; green mesh installed; all 3 towers reached 1st floor. | Completed |
| Mid October 2026 | Tower B3 poured 3rd floor slab; Tower B2 poured 2nd floor slab under continuous shifts. | Completed |
| Early November 2026 | Tower B3 completed 4th floor slab; site clearing for low-rise Clubhouse and 30-ha expansion parcel. | Ongoing |
| Q4/2027 (Expected) | Projected apartment handover to homeowners as announced on site billboards. | Scheduled Target |
| 2028 (Expected) | Anticipated processing and issuance of official ownership certificates (pink books). | Future Target |
Expected handover schedule and inspection advice
Site billboards at Gladia Heights indicate an expected apartment handover in the fourth quarter of 2027 (Q4/2027). The project possesses key statutory documentation, including Official Letter 26381/SXD-PTDT and Land Use Certificates DQ 128066 and DQ 128067 issued in November 2024.
Prospective purchasers should review the formal payment schedules published by Keppel and Khang Dien. Payment plans feature stages tied directly to verified construction milestones. When reviewing options, buyers are advised to request official contractor milestone reports for their specific tower rather than relying solely on overall site photos.
Explore more projects with DND Realty
Updated 11.11.2026Gladia Heights Project OverviewGladia Heights by Keppel Land & Khang Dien: 3 towers of 15 storeys, 616 units, Vo Chi Cong corridor. Prices from VND 83M/m². Hotline +84 906 873 708.Read in Vietnamese
Updated 11.11.2026Eaton Park Gamuda Land Project GuideEaton Park foreign buyer guide: 3.7 hectares, six towers, 1,968 apartments, ownership notes, legal documents and construction progress. DND Realty 0906.873.708.Read in Vietnamese
Updated 20.11.2026The Prive Bluemarq Project ProfileRead in Vietnamese
Updated 28.10.2026Imperia Sensa Park Project GuideImperia Sensa Park by MIK Group delivers 922 apartments and 93 landed villas on Vo Chi Cong. Explore 2026 master plans, layouts, and prices at DND Realty.Read in Vietnamese
Updated 13.11.2026Eaton Park vs Gladia Heights vs The Prive ComparisonCompare Eaton Park, Gladia Heights and The Privé: 2027-2028 handover schedules, site progress, legal documents and payment terms from DND Realty.Read in Vietnamese
Updated 13.11.2026Imperia Sensa Park vs Gladia Heights ComparisonImperia Sensa Park vs Gladia Heights on Vo Chi Cong Street: compare 2BR prices from 6 billion VND, legal status, amenities, and 2027-2028 handover dates.Read in Vietnamese Frequently asked questions about Gladia Heights progress
What is the current construction status of Gladia Heights in November 2026?
In early November 2026, Tower B3 completed its 4th floor slab and prepares for the 5th floor. All 3 towers have finished retail podiums and are covered in green safety netting, with 3 Potain cranes operating.
Who is the general contractor and developer of Gladia Heights?
The developer is Doan Nguyen Real Estate Investment and Trading Company Limited, a joint venture between Keppel and Khang Dien. An Phong Construction serves as general contractor.
How many towers make up Gladia Heights and what are their official names?
Gladia Heights comprises 3 towers rising 15 storeys: Tower B1 (The Future), Tower B2 (The First), and Tower B3 (The Advanta), providing 616 luxury apartments and 23 retail units.
Where is the Gladia Heights show unit located and what are the visiting hours?
Show units opened on June 14, 2026, and welcome visitors daily from 08:30 to 17:30 at the project sales gallery along Vo Chi Cong Road, Binh Trung Ward.
When is Gladia Heights expected to be handed over to buyers?
Site billboards announce an expected handover in the fourth quarter of 2027 (Q4/2027), subject to formal milestone notices from Keppel and Khang Dien.
How does DND Realty assist foreign property buyers with project inspections?
DND Realty arranges guided site visits, provides aerial flycam footage, and assists foreign buyers with verified legal documents and SPA registration procedures.
Consult with DND Realty property advisors
DND Realty provides ongoing field monitoring of real estate developments in East Ho Chi Minh City. International buyers seeking project documents or virtual site viewings are invited to contact our team.